Sec. 28.009. RIGHT TO SUSPEND WORK.

Property Code § 28.009

(a) If an owner fails to pay the contractor the undisputed amount within the time limits provided by this chapter, the contractor or any subcontractor may suspend contractually required performance the 10th day after the date the contractor or subcontractor gives the owner and the owner's lender written notice:

(1) informing the owner and lender that payment has not been received; and

(2) stating the intent of the contractor or subcontractor to suspend performance for nonpayment.

(b) For purposes of Subsection (a), the contractor or subcontractor must give the owner's lender the written notice only if:

(1) the owner has obtained a loan intended to pay for all or part of the construction project;

(2) the lender has remitted funds, including acquisition funds, for construction purposes;

(3) the loan obtained:

(A) is evidenced by a promissory note secured by a deed of trust recorded in the real property records of the county in which the real property that is the subject of the contract is located; and

(B) is not only for the acquisition of personal property or secured only by a security instrument;

(4) the owner or lender, at the lender's option:

(A) securely posts not later than the 10th day after the date construction commences a sign on the project site in a prominent place accessible to each contractor, subcontractor, and supplier that states the lender's name, address, and the person to whom any notice should be sent; and

(B) maintains the sign during the pendency of the construction project;

(5) not later than the 10th day after the date construction commences, the owner or lender, at the lender's option, provides a written copy of the notice prescribed by Subdivision (4) to the contractor and any subcontractor or supplier identified by the contractor by depositing the notice properly addressed in the United States mail, first class, postage paid; and

(6) not later than the 10th day after the date a subcontractor or supplier performs labor or furnishes materials or equipment for the construction project, the owner, contractor, or subcontractor provides a written copy of the notice prescribed by Subdivision (4) to the subcontractor or supplier.

(c) A contractor or subcontractor who suspends performance as provided by this section is not:

(1) required to supply further labor, services, or materials until the person is paid the amount provided by this chapter, plus costs for demobilization and remobilization; or

(2) responsible for damages resulting from suspending work if the contractor or subcontractor has not been notified in writing before suspending performance that payment has been made or that a good faith dispute for payment exists.

(d) A notification that a good faith dispute for payment exists provided under Subsection (c) must include a list of specific reasons for nonpayment. If a reason specified includes labor, services, or materials provided by a subcontractor that are not provided in compliance with the contract, the subcontractor is entitled to a reasonable opportunity to:

(1) cure the listed items; or

(2) offer a reasonable amount to compensate for listed items that cannot be promptly cured.

(e) This section does not apply to:

(1) a contract for the construction of or improvements to a detached single-family residence, duplex, triplex, or quadruplex; or

(2) a contract to improve real property for a governmental entity.

(f) The rights and remedies provided by this section are in addition to rights and remedies provided by this chapter or other law.

Added by Acts 1999, 76th Leg., ch. 805, Sec. 4, eff. Sept. 1, 1999.

Source details
canonical id
tx-statute:pr:28.009
provision id
tx-statute:pr:[email protected]
version id
tx-statute:pr:[email protected]~bdae0d989f3b44ff
record id
tx-statute:pr:[email protected]
document id
tx-statute-chapter:pr:28
record sha256
d74ec3334d60032bc0013c329bb5316fe81c331da7a22cc9b6a7913e7cee1b85
anchor id
p-28-009-62576-53841
legalcore record url
https://legalcore.example.invalid/tx/statutes/pr/sections/28.009/62576.53841

Source locations are recorded for verification and are not links.

References in this section

  • Sec. 28.009. RIGHT TO SUSPEND WORK.
    Reference details
    original href
    https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm#28.009
    target fragment
    28.009
    source context
    paragraph
    resolution reason
    unique prepared provision #28.009 in tx-statute-chapter:pr:28
    expected target id
    tx-statute:pr:28.009
    source document id
    tx-statute-chapter:pr:28
    source provision id
    tx-statute:pr:[email protected]
    target document id
    tx-statute-chapter:pr:28
    target provision id
    tx-statute:pr:[email protected]
    target version id
    tx-statute:pr:[email protected]~bdae0d989f3b44ff
    candidate
    tx-statute:pr:[email protected]
    resolution status
    resolved

    Source locations are recorded for verification and are not links.

Cited by

  • PR § 28.009 cites it as “Sec. 28.009. RIGHT TO SUSPEND WORK.”
    Reference details
    original href
    https://statutes.capitol.texas.gov/Docs/PR/htm/PR.28.htm#28.009
    target fragment
    28.009
    source context
    paragraph
    resolution reason
    unique prepared provision #28.009 in tx-statute-chapter:pr:28
    expected target id
    tx-statute:pr:28.009
    source document id
    tx-statute-chapter:pr:28
    source provision id
    tx-statute:pr:[email protected]
    target document id
    tx-statute-chapter:pr:28
    target provision id
    tx-statute:pr:[email protected]
    target version id
    tx-statute:pr:[email protected]~bdae0d989f3b44ff
    candidate
    tx-statute:pr:[email protected]
    resolution status
    resolved

    Source locations are recorded for verification and are not links.

Citations show recorded connections only, not legal effect or validity.